Top

WHAT IS JTA

ORGANIZATION

JOURNAL

TUNNELLING DATA

LATEST TUNNELLING TECHNOLOGY

CONFERENECE & EVENT

 

 

 

                                                                                                                     

JOURNAL OF JTA

 

TUNNELS AND UNDERGROUND is the official monthly journal of JTA. The followings are abstracts of papers.

 

Tunnels and Underground  - CONTENTS

2005

2004

2003

2002

2005

[Vol. 36, No.8 August ] 2005

Excavation of Takaoka Tunnel of Hokuriku Shinkansen under Road Tunnel using Measurement System

By Junichi Yorita, Japan Railway Construction, Transport and Technology Agency

The north section of Takaoka Tunnel of Hokuriku Shinkansen (Superexpress Railway) passes under Nakano Tunnel crosswise, which is a tunnel of Shiga-Nakano Expressway leading to Shiga Highlands. Nakano Tunnel was complete in 1998 before Nagao Winter Olympic Games and is now under operation. Before the construction of Nakano Tunnel, we discussed the measures to protect this road tunnel against the impact of excavation of Takaoka Tunnel with the owner of Nakano Tunnel. According to the decision of this meeting, the structure of secondary lining of Nakano Tunnel in the crossing area is the RC one. And, during the excavation of Takaoka Tunnel, several kinds of measurement were done in Nakano Tunnel. This paper reports the measures to protect Nakano Tunnel and the measurement system adopted in this project.

 

Breakthrough of Twin Tunnel with Large Section in Fractured Zone, project of Fuji-River Tunnel of Tomei Expressway No.2

By Masahiko Ohnishi, Japan Highway Public Corporation

Fuji-River Tunnel of Tomei Expressway is a twin tunnel having the length of 4500 m. The middle of this tunnel that is located in the squeezing ground having fractured zone with faults. The competence factor of ground in this section is 0.3 to 0.7. We were concerned about the damage of lining by the pressure of squeezing ground and negative impact to the preceding tunnel by the excavation of following tunnel because the construction of twin tunnel having a large section in this kind of ground condition was unprecedented. Due to the above-mentioned reasons, the TMB pilot and enlargement excavation method was adopted in this project. The construction of this tunnel was successful without the replacing of timbering. This paper introduces the concept of design, the excavation method and the field observation adopted in this project.

 

Protection of Underground Station against Rising of Ground Water Table

By Kenichi Kusumi, East Japan Railway Company, LTD.

Ueno Underground Station of Tohoku Shinkansen (Superexpress Railway), which was complete in 1985, has the depth of 30m and the box frame substructure of 4 stories and 6 spans. The deformation of the lowest slab and the uplifting of this station were expected due to the rising of water table. The counterweight method using ingots of steel and the permanent ground anchor method were adopted to prevent the uplift of station. These works were done close to railway lines under operation. This paper presents these measures.

 

Construction of New Intake Water Tunnel close to Existing Water Tunnel

By Saburo Ishii. Shimizu Corporation

Before the raising works of Shin-Katsurazawa Dam, the new intake water tunnel was constructed close to the existing water tunnel. In this project, some measures to mitigate the vibration were adopted. We recognized the following results through the construction of this tunnel

1) Regardless of performance of center-cut or side holes, the blasting by electronic detonators made the maximum vibration velocity in different stages. The K-value by this system is approximately equal to the one of center-first cut blasting using usual detonators.

2) If the distance is less than 15 m, the measured value of vibration velocity and the expected value of it by the formula is largely different. This phenomenon would be caused by the linear relation between the vibration velocity and the K-value (the more the vibration velocity, the more the K-value).

3) The K-value is anisotropic due to the direction of transmission of vibration. This value in transverse direction is smaller than the one in longitudinal direction.

4) If the distance between the existing tunnel and the tunnel to be excavated is less than 10 m, the mechanical excavation was adopted because the drill and blast method was inappropriate.

 

Experimental Study on Burn-Cut Method using Small Holes

By Ko Kawano, Dyno Nobel Japan, Co., LTD.

This paper discusses the study on the burn-cut method for the center-cut using shot holes and relief holes.

The diameter of relief hole is same as the one of shot hole and one shot has 4 to 6 relief holes. We studied the mechanism of fracture of face by observing development of cracks. It is clarified that, due to the proper selection of ratio of numbers between shot holes and relief holes, the cracks are developed both in longitudinal direction and in transverse one to make center-cut.

 

 [Vol. 36, No.7 July] 2005

Breakthrough of Iiyama Tunnel using New Support System in Swelling Ground- Konari and Itakura Sections of Iiyama Tunnel Project of Hokuriku Shinkansen (Superexpress Railway)

By Atsushi Nakamura, Japan Railway Construction, Transport and Technology Agency

Iiyama Tunnel having the length of 22.2 km is located between Nagano Prefecture and Niigata Prefecture. The construction project of this tunnel is divided into 6 sections including Konari Section and Itakura Section. These two sections are in fractured zones with faults and swelling ground (the disturbed zones). The new support system using the high strength initial support and the rapid construction method of secondary lining was adopted to excavate this tunnel in the disturbed zones and the analysis to predict the ground movement was done. The tunnel was safely excavated using this system. The convergence was up to 50 o. This paper reports the new system adopted to this project and the result of measurement.

 

Application of Chemical Injection Method using Inorganic Ultrafine Particles to Oshino Tunnel

By Yoichi Wakao, Yamanashi Prefecture

Oshino Tunnel in Yamanaka-Ko Oshino Fujiyoshida Prefectural Road having the length of 757 m joins Oshino Village, Yamanashi Prefecture and Fujiyoshida City.

This tunnel was constructed with the NATM.

The AGF Method (the All Ground Fasten Method) and the reinforcement method as the auxiliary methods at the foot part was adopted at the portal, where the geology was unsolid sediment of volcanic ash with scoria, and the forepoling method was adopted in the transition section from unsolid ground to solid one. They were to stabilize the face and lining. And, the chemical injection method using ultrafine particles with good gel property was adopted to control the inflow of ground water into the tunnel without the negative impacts to ground water. This paper introduces this chemical injection method.

 

Freezing Method applied to Electric Cable Duct Tunnel - Tunnel Project for Ultra-High Voltage Cable in Ushijima Town by Chubu Electric Power Co., Inc.

By Toshio Takagi, Chubu Electric Power Co., Inc.

The ultra-high voltage cable tunnel project in Ushijima Town, 30 km north from JR Nagoya Station, is one part of the urban redevelopment plan in Ushijima South District where is in the residential area in the Category I. This urban redevelopment plan has been promoted by the redevelopment association comprising Chubu Electric Power Co., Inc. and other landowners since 2000. The Phase One of this plan consisted of the destruction of buildings and the construction of electric cable tunnel, substation and related facilities, and was completed in the end of 2003.

.The electric cable tunnel construction project consisted of the construction of tunnel and shaft to extend the existing electric cable of 275 kV (Kaifu-Meijo Line) and draw it into newly built underground ultra-high voltage substation of Chub Electric Power Co., Inc, using the πjointing system.

This paper reports the freezing method to protect the joint part of this tunnel 30 m below ground and how to predict the ground movement caused by to the freezing method, and the measures against it.

 

Extension Project of Tozai Line of Kyoto Subway

By Mamoru Furukawa, Kyoto Municipal Transportation Bureau

This paper reports the shield tunnelling project of Tozai Line of Kyoto Subway between Nijo and Tenjingawa, which began on November. 2002.

In Nijo West section, the tunnel is excavated with twin single-track shields. The belt conveyor system using Hume pipes was used for the efficient mucking from the shaft to the narrow construction yard on the surface. In the shaft, the SEW System (the Shield Earth Retaining Wall System) was adopted to save manual works.

In Nishi-Oji West section, the tunnel was excavated with a double-track EPB-shield. The excavation works were done with the serious drive control without auxiliary methods to mitigate the impact against the existing water pipe crossing this tunnel that was constructed in 1960s.

Excavated soil after the treatment was reused in the invert of tunnel to save the cost and mitigate the emission of the greenhouse gases.

 

Fire-Proof System applied to Road Tunnel - Akita Central Road Tunnel constructed by Shield Tunnelling Method

By Takeshi Honda, Akita Prefecture

The measure against fires in tunnel is a worldwide theme and the structural approaches and the methods to verify the performance of them are not yet established.

Akita Central Road joins the east district of JR Akita Station and the west one. Most sections of it were constructed with the shield tunnelling method. In this shield tunnel, the newly developed fire-proof system not using the secondary lining applied to the segmental lining was used to mitigate damages by fire caused by traffic accident. We made a heating test using a full-scale model and verified the performance of this system. This paper reports the fire-proof structure applied to Akita Central Tunnel and proposes the concept for the fire-proof system in tunnel.

 

[Vol. 36, No.6 June] 2005
Breakthrough of Hakkoda Tunnel in Tohoku Shinkansen (Superexpress railway)

Hirotoshi Kimura, Japan Railway Construction, Transport and Technology Agency

The excavation works of Hakkoda Tunnel in Tohoku Shinkansen, which is located between Temmarin Village, Aomori Prefecture and Aomori City, was complete on February 27, 2005. The length of this tunnel is 26.455 km and the longest among tunnels excluding undersea tunnels in the world.

This tunnel project was divided into 6 sections. The excavation began on March, 1998 and ended on February, 2005. The measures against environmental pollution by acid ground water were required because this tunnel penetrated fractured zones and spring water zones in metamorphic rocks made by the volcanic action of Hakkoda Mountain.

This paper reports the construction program and construction results of this project.

 

Shield Tunnel Construction adjacent to Existing Structures - Kami-Ochiai Section of Metropolitan Circular Expressway

Isao Kamegaya, Metropolitan Expressway Public Corporation

Kami-Ochiai Expressway Tunnel is twin one constructed with two slurry shields with a diameter of 11.42 m. This tunnel is adjacent to existing tunnels and lifelines such as the subway, the communication tunnel of NTT and the gas pipe and the shields passed beneath the ventilation shaft for this expressway under construction with the clearance of 1.0 m and with the distance of 244 m. The intelligent construction system made this project successful without the negative impact against the existing substructures. This paper presents the construction records of this shield tunnel project.

 

Construction of Subway Station by Cut & Cover Method under Sewer Main - Takadamachi Station Section of Yokohama Municipal Subway Line No.4

Transportation Bureau, City of Yokohama

Yokohama Municipal Subway Line No.4 is one part of the circular line of railway network in Yokohama City and will join Hiyoshi Station of Tokyu-To-Yoko Line, leading to Shibuya, Tokyo, and Nakayama Station of JR-Yokohama Line, and have a length of 13.1 km and 10 stations.

Takadamachi Station, next to Hiyoshi Station of Tokyu-To-Yoko Line but one, is under construction by the cut and cover method. This paper reports the construction works of this station including the undermining method and others (the suspension system or the supporting system) to protect Takada Storm-Water Sewer Main overlying this station.

 

Application of Machine for Pipe Jacking Method convertible into Shield Machine -

Yagawa Storm-Water Sewer Main

Tsuneto Takaso, Tokyo Metropolitan Government

The bored tunnelling method is often adopted to construct sewers in Tokyo in consideration of narrow construction space, existing substructures and traffic condition on surface. These conditions lead to the difficulty to secure construction yard and the adoption of sharply curved alignment. In Yagawa Sewer Main Project, the machine for the pipe jacking method convertible into the shield machine is adopted to settle the problems under above-mentioned construction conditions, mitigate the negative impacts against environment and reduce the construction cost. This paper introduces the planning of this project.

 

Study on Risk Management and Prediction of Ground Movement by Tunnel Excavation in Gravel Layers

Ko-ichi Takahashi, Japan Railway Construction, Transport and Technology Agency

The chemical injection method with the specific resistance tomography method and the deep well method was adopted to construct the station by jointing the shaft and shield tunnel in the aquifer of Tokyo-gravel layer to mitigate the risk of seepage water and secure safe works. And, the two-dimensional FEM and three-dimensional one were adopted to predict the ground behavior in consideration of the process of construction works. After the construction, the reversed FEM analysis using non-liner elasto-plastic model was done. This paper proposes the two dimensional model to predict ground behavior simply and realistically.

Abridged Japanese translation of "Risk in Tunnelling: Analysis and Procedures relating to the Zimmerberg Tunnel" by Prof.Dr.K.Kovari, Tunnel 6/2000 issued by STUVA

Translated by Tatsutoshi Kondo, Geofront Partners

This paper discusses the following themes.

1)      To define technical terms on risk and uncertainty to have common recognition on them

2)      To quantify the risk by the product of amount of damage and the incidence (probability) of risk

3)      To identify certainties and uncertainties in tunnel project and evaluate them without bias

4)      To mitigate the risks by understanding of all of persons in charge of tunnel project on safety program

Theme No.4 is important not only for success of tunnel project but also for management of organization of client or contractor. Theme No2. suggests damages by unexpected risk. This paper proposes the approach to identify risks on irreversible tunnel project that it is difficult to predict with the probability method.

 

[Vol. 36, No. 5 May]  2005

Construction of Tunnel having Very Large Section in Unsolid Ground  South Section of Minoo Tunnel

 By Norishige Taketomo, Osaka Prefectural Road Public Corporation

 Minoo Tunnel is one part of Minoo toll road and the length of south section of it is 2.2 km. It was constructed in Osaka StrataGroup, unsolid ground, and its excavation section area was up to 313 m 2. The construction records of heading before the excavation of main tunnel contributed to the design and investigation of construction method of main tunnel. The side wall drifts followed by benching method, the top drift followed by excavation method and the side drifts followed by excavation method were choices and the last one was selected.

 The pipe roof method was adopted as an auxiliary method if the section area was over 300m 2, and the forepoling and the face bolting were done if it was 300 m 2 or less. This paper reports the construction records of this tunnel with a very large section including the measurement.

 

Construction of Connection Pass under Entrance/Exit of Subway constructed in Soft GroundPass jointing Ichinoe Station of Shinjuku Line, Tokyo Metropolitan Subway, and Bicycle Parking

 By Masaki Sano, Tokyo Metropolitan Government

 This paper presents the construction of pass jointing the underground bicycle parking having the capacity of 2,500 bicycles under construction and the entrance/exit of Ichinoe Station under operation. Edogawa Ward, Tokyo, awarded this project to Transportation Bureau of Tokyo Metropolitan Government. Transportation Bureau of Tokyo Metropolitan Government adopted the roof and culver method the R&C method to construct the pass without the interference to passengers using the entrance/exit. This paper also reports the outline of R&C method.

 

Strategy of Tunnel Construction in squeezing Ground

 By Hiroshi Takahashi, Sumitomo Mitsui Construction Co.,Ltd.

 Tunnelling Engineer in charge designs support type of tunnel to be constructed in squeezing ground , where troubles and accidents often happen during tunnel construction, and make construction program including construction method, according to his own experience. We collected the construction records of tunnels in squeezing ground and classified them systematically. This study proposes the standards for design and construction method to execute road tunnels having two lanes and Shinkansen Superexpress tunnels in squeezing ground.

 

Damages of Railway Tunnels by Niigata Chuetsu Earthquake

 By Mitsuru Shimizu, East Japan Railway Co., Ltd.

 The transportation systems such as Joetsu Shinkansen Superexpress railway, Joetsu railway, National Road No.17 and 117 were seriously damaged by Niigata Chuetsu earthquake on October 23, 2004. The damages of tunnels having high performance of aseismicity characterized this earthquake. They occurred not only at portals but also in intermediate section of tunnels. This paper reports the status of damages of railway tunnels and the repair works.

 

[Vol. 36, No.4 April] 2005

Extruded Concrete Lining Method applied to Mountainous Tunnelling  Sambongihara Tunnel Project of Tohoku SinkansenSuperexpress Railway

 By Mikio Sasaki, Japan Railway Construction, Transport and Technology Agency

 Sambongihara Tunnel of Tohoku Sinkansen having a small cover is located in unstable ground with high water pressure. This tunnel was excavated with the NATM and had some troubles such as collapses at face. To settle these troubles, the extruded concrete lining methodthe ECL method using a TBM is applied to the last 3000m of this tunnel. In this section, the initial lining is performed with the castinplace concrete using the extruded concrete method which sustains the ground pressure, and the secondary one as a nonstructural member is done after the completion of convergence.

 The function of extruded concrete lining corresponds to the one of the shotcrete lining of NATM. This system is named the SEMS in this project.

 This paper explains the concept of the SENS and reports the performance early stage of this project.

 

World's Largest EPB Shield applied to Metropolitan Circular Line

 By Hiroshi Dobashi, Metropolitan Expressway Public Corporation

 The world's largest EPB shield is adopted in the Shinjuku Line of Metropolitan Circular Expressway. This paper reports the outline of this project including the construction records such as how to stabilize the face, how to manage the earth pressure in chamber and control the plasticity of excavated materials and their mucking system, and the development of visual system in the chamber. This paper also presents the tunnelling technologies such as the novel material shield cuttable tunnel wallNOMSTsystem, the long distance shield drive and the coincident construction of shield drive and the deck slab inside tunnel.

 

Shield Tunnelling Project using Circular Steel Liner Plate Shafts and fourpiece segmental LiningOchiaiRiver StormWater Sewer Main Project

 By Mitsuo Ito, Tokyo Metropolitan Government

 This paper introduces new tunnelling technologies adopted in OchiaiRiver stormwater sewer main project by the shield method such as the shield starting and arrival method using the circular steel liner plate and the fourpiece segmental lining, aiming at the cost saving.

 The shield-cuttable material was used at the parts of shield start and arrival in the shafts. The convex and concave joint was adopted in the segmental ring having smooth inner face. At the current stage, these technologies contribute to the success of this project.

 

Nakanoshima New Subway Line Construction Project

 By Motonori Nagataki, Nakanoshima Rapid Railway Co., Ltd.

 Nakanoshima New Subway Line having the length of 2.9 km and deep cover is located at the center of Osaka City and will join Keihan Line. This new line will pass under three existing subway lines and a river, and have four stations to be constructed by the cut and cover method and doubletubeshingletracks by the shield method. The geology in this section is waterbearing gravel and soft clay. Keihan Line will be relocated at the joint part to this new line. The construction of this new line began in 2003 and will complete in 2008. This paper presents the outline of this project.

 

Bosporus Rail Link Project  World's Deepest Immersed Tunnel Project

 By Hideki Sakaeda, Pacific Consultants International Co., Ltd

 Bosporus Rail Link Tunnel will be the world's deepest immersed tunnel. The construction of this tunnel began on August 27, 2008. The followings feature this project.

1 The railway system of this project including the tunnel crossing Bosporus Strait has a double track and the length of 13.6 km.

2 The depth between the surface of seawater and the bottom of tunnel is up to 60 m.

3 The tide of Bosporus Strait is very fast.

4 This railway system improves the commuting condition in Istanbul.

5 The fault that would cause big earthquake is near this area.

 This project is done with the ODA from Japan. After the completion of this railway system scheduled on March 2010, the Oriental Express, whose terminal station is now Sirkeci will cross Bosporus Strait.

 

Inspection of Voids between Lining and Ground using Rotary Percussion System

 By Kenji Oshima, Japan Highway Corporation

 Conventionally, the coredrilling method has been used to investigate voids between tunnel lining and ground. This method needs long time and much cost relatively. The newly developed PVM system using rotary percussion has settled these problems. This system having the function of rapid drilling gives us the precise condition of lining and status of voids between lining and ground with short time relatively. This paper presents this system.

 

[Vol. 36, No. 3 March] 2005

Tunnel Construction in unstable Ground using Ground Improvement Method  Hokuriku Shinkansen Super Express Railway, Kurobe Tunnel  No.1

 By Takahiko Yabe, Japan Railway Construction, Transport and Technology Agency

 Kurobe Tunnel No.1 of Hokuriku Shinkansen with a length of 920 m is located in Kurobe City, Toyama Prefecture and excavated in the unstable alluvium cone with a small cover of 2 to 10 m. The construction yard was made at the intermediate point of this tunnel. In consideration of the ground condition and environmental one, the forepoling method with the chemical injection as an auxiliary method was adopted between the Takasaki side portal and the intermediate point the Section A and the ground improvement method was done between the Toyama side portal and the intermediate point the Section B.

 This paper presents the construction program and the construction records including the measurement works in the section B.

 

Breakthrough of Tunnel Construction in Landslide Zone with small Cover using Intelligent Construction System  Tomie Expressway No.2, Inasa Tunnel No.2

 By Satoshi Tayama, Japan Highway Public Corporation

 Mountainous tunnel excavation in small cover often causes landslide. The north portal of Inasa Tunnel No.2 has a small cover and is located in the landslide zone. In this tunnel project, the mechanism of landslide had to be clarified and the measures to prevent landslide at the north portal had to be done. This paper discusses the design and construction for tunnel in landslide zone.

 

Subway Project in Bangkok  Construction of Chaloem Ratchamongkhon Railway Line

 By Yoshio Otsuki, Tokyo Metro Co., Ltd.

 The first subway in Bangkok has begun the operation since July, 2004. This project was one by the ODA from Japan and the tunnelling technology in Japan contributed to this project. In this project, the government was in charge of the construction project of this subway and the private sector is in charge of its operation.

 This paper reports the underground technologies applied to this project such as the rapid inverted construction method and the diaphragm wall method using steel boxes to construct stations, and the shield tunnelling and the technologies to remove obstructs to construct bored tunnels.

 

Underground Docking Method using Freezing Method  Minamidai Sewer Project in Tokyo

 By Koushi Shibayama, Tokyo Metropolitan Government

 In Minamidai sewer project, Minamidai branch sewer with a diameter of 4.43 m constructed by the shield tunnelling joined the bottom of Wadayayoi sewer main with a diameter of 9.4 m having a function of storage at the depth of 50 m. The opening of joint part by the removal of segments of the sewer main is oval shaped its lateral diameter is 4.8 m and its vertical diameter is 6.0 m. At the docking zone, the freezing method was adopted to stabilize ground and to prevent water inflow after removing segments. During the docking works, the measurement of opening part and the control of temperature in the ground at the joint part ware strictly done.

 This paper reports the planning, design and construction of docking works.

 

Measurement of Behavior of long Forepoling Pipe in Site

 By Haruo Sasao, Tekken Corporation

 This paper reports the results of analysis of measurement of tunnel constructed with the All Ground Fasten method as an auxiliary method, which is one of the forepoling methods using long steel pipes. The purpose of measurement was to clarify the support mechanism of forepoling pipes and the behavior of ground. The deflection of forepoling steel pipes to find out vertical displacement at tunnel crown of ground ahead of face, the axial force of forepoling steel pipes at tunnel crown to recognize their axial force and bending moment were measured. In the section without the forepoling, the measurement of deflection of PVC piles at tunnel crown was performed. The results of measurement of deflection of pipes in the section with forepoling pipes and the one without forepoling pipes were compared in this study.

 

[Vol. 36, No. 2 February] 2005

Application of Face Bolting to Box Pulling Method underpassing Railway  RoadUnderpassingRailway Project in JRKaminopporo Station

 By Yasuhito Konishi, Hokkaido Railway Company

 The Kaminopporo BV Project is the construction one that a new road underpasses the existing JRChitose Railway. The geology in this site is saturated clayey fill. In consideration of such ground condition, in this project, the face bolting method was adopted to stabilize the face instead of the ground improvement such as chemical injection that would gives negative impacts to the railway. Before the application of this method, the numerical simulation was done to clarify the mechanism of fracture of ground.

 This paper reports the consistency of the abovementioned simulation before construction and the results of measurement during construction, and the drilling method as a appropriate method in this project for the costsaving and reduction of construction period.

 

Construction of GlassesShaped Twin Tunnel without Side Drifts and temporary Lining of Pilot Tunnel  Daimonji Tunnel Project of Main Local Road IbarakiKameoka Line

 By Akio Takahashi, Osaka Municipal Government

 Usually, in execution of glassesshaped twin tunnel, center pillar and side walls are complete after the construction of center drift and side drifts and lining of them. In the Daimonji Tunnel Project, the construction of glassesshaped twin tunnel was successfully performed without side drifts and temporary lining of pilot tunnel for the cost saving, reduction of construction period and improvement of quality of structure. This paper presents the procedure of design and the construction with the measurement.

 

Underpinning of Foundation of Subway Ginza Line in Shibuya Station  Subway No.13 Project

 By Takaaki Nishimura, Tokyo Metro Co., LTD

 Subway No.13 in Tokyo that is now under construction will start from Ikebukuro Station and reach Shibuya Station through MeijiDori Street with the length of 8.9 km. Subway Ginza Line has a viaduct structure and overpasses Shibuya Station with 6 piers of 2column type in MeijiDori Street that has heavy traffic volume. These piers have footing foundations, which height is 1.0 m, with pine piles. These piles are at the depth of G.L.0.8 to 1.2 m and located in the construction section of Subway No.13 to be executed by the cut and cover method. They have to be removed before the construction of Subway No.13. Due to this construction condition, the load of Ginza Line shall be replaced by the underpinning method using new beams to be added to the both side of each footing and new piles in consideration of the traffic condition.

This paper introduces the planning of replacement works of footings.

 

Construction of Sewer Tunnel Project by Shield Method and Public Relations on it for Resident  Arisugawa Sewer Main in Kyoto City

 By Takashi Dairaku, Kyoto Municipal Government

 The project of Arisugawa Sewer Main is one part of the storm water storage project in Kyoto City. This tunnel is located under the narrow road leading to the sightseeing site. In consideration of environmental matters, this sewer main was constructed by the shield method with long distance driving to minimize works on the ground surface and without the secondary lining to reduce the construction period. The facilities in the site were covered with soundproof structures.

 Kyoto Municipal Government organized the public relations on this project such as the site visits and explanatory meetings for the resident actively.

 This paper presents the outline of shield tunnel works and the public relations for resident.

 

Monitoring System of Tunnel Lining using Optical Fiber

 By Yoshiyuki Kojima, Railway Technical Research Institute

 Usually, the measurement of convergence of tunnel or width of cracks using strain gauges and crack gauges is done to monitor deformation of lining and negative impacts given to existing structures by tunnel excavation. If this method is adopted to monitor the condition of long tunnel for long time, it needs great efforts and energies. To settle this matter, we study on the remote control monitoring system using the optical fiber. This system can monitor the change of strain of lining continuously.

 This paper introduces our studies, especially, the loading test using miniature model, the insitu test and measurement management system.

 

[Vol. 36 No. 1 January] 2005

Application of Protection Embankment Method to Tunnel Excavation having very shallow Hokuriku Shinkansen Superexpress Line, Koushasan Section

 By Junichi Yorita, Japan Railway Construction, Transportation and Technology Agency

 The south section of Koushasan Tunnel of Hokuriku Shinkansen Railway Project has a length of 1,500 m and the cover within the distance of 280m from the portals is up to 5 m and the one within the distance of 80 m from the portals ranges from 1 to 2 m. In this construction condition, the protection of tunnel cover area is absolutely necessary using the embank method. On the embankment to be constructed, orchards, roads and waterways will be located and the negative impact by tunnel construction to them shall be mitigated. In the design stage, the traffic load to the tunnel having the very shallow cover shall be considered. This paper reports the tunnel construction using the protection embank method.

 

Construction of twin tunnel in diluvial sand with shallow cover Tobuki Tunnel of ShinTakiyama Kaido Street in MinamiTama 

 By Takayuki Tanaka, Tokyo Metropolitan Government

 Tobuki Tunnel is one part of ShinTakiyama Kaido Street, a glassesshaped twin tunnel, and has a length of 600 m jointing Sairicho of Hachioji City and Akiru Bridge of Akiruno City, and a shallow cover. This tunnel was constructed in the diluvial sand strata by the NATM and passes a river. One subject of this tunnel project was to save the construction period because the construction of twin tunnel has relatively many steps. To solve this matter, the closure of invert of the preceding tunnel and the excavation of following tunnel were done coincidently. Before the construction, the safety of tunnel structure, especially, the one of center pillar, was checked by the FEM. This paper describes the major points of construction, the measures to pass the river and the measurement during the construction.

 

Water supply tunnel by DoubleJack Shield Method in Tama, Tokyo

 By Tsuneo Sato, Tokyo Metropolitan Government

 TamaKyuryo Water Supply Line Main joins Hijirigaoka Water Work Station in Tama City and Haijima Pumping Station in Akishima City, and has a length of 31.6km and a diameter of 1500o. The first stage of this project is a tunnel construction of water supply with a length of 12.6km between Hijirigaoka Water Work Station and Yarimizuoyama Water Work Station. The first stage of this project is to construct a water supply tunnel by the shield tunnel method, jointing Yarimizuoyama Water Work Station and Oyamacho in Machida City. This paper presents the outline of the first stage of the first section such as the planning of alignment and the process of selection of construction method In this project, the doublejack shield tunnelling method which enables the coincident works of the shield advance and the assembling of segmental lining is adopted.

 

Tokyo Metro Line No.13 by Shield Tunnelling The last Subway Line in Tokyo

 By Ikuo Fujiki, Tokyo Metro Co., LTD

 Tokyo Metro Co., LTD is now constructing Tokyo Metro Line No.13 between Ikebukuro and Shibuya, which will be under operation in 2007. This subway line will be the last one to be constructed in Tokyo area by Tokyo Metro Co., LTD which has constructed the subway network of Tokyo area since the execution of Marunouchi Line. Technically, integrated tunnelling technologies and newly developed ones in Japan to construct subway tunnels and stations are adopted in this project. This paper introduces the outline of tunnel construction by the shield tunnel method in this project.

 

Development of Side Ramp Junction Construction Technology by Bored Tunnelling Method

 By Toru Terayama, Tokyo Metropolitan Expressway Public Corporation

 Junction which joins expressway in underground and roads at grade is usually constructed with the cut and cover method. Tokyo Metropolitan Expressway Public Corporation MEX developed the safe and rational construction method of ramp junction and researched reliable structure of it. This method is to enlarge underground space by the bored tunnelling method such as the shield method, and enables to construct ramp junction jointing shield tunnel and surface in densely populated urban areas where shaft cannot be excavated by the cut and cover method. MEX proposes the technology to construct ramp junction by the bored tunnelling method in this paper.

 

 

2004

[Vol. 35 No. 1 January] 2004

Start with the Regionally Longest On land Tunnel Construction in KyushuChikushi Tunnel on kyushu Shin-kansen Linepp7

 By Masayoshi Miura, Japan Railway Construction, Transport & Technology Agency

 This is a mountain tunnel of 11.9km length, the longest of all the existing tunnel on the Kagoshima Route of Kyushu Shin-kansen. The proposed rail alignment is designed to make detour from the dam catchment basin because the dam site has been well known as an important 'pot' for water reserve in the Fukuoka Urban Area. The site geology is featured mainly by tough granite. However, its local geology was foreseeable as the deteriorated at five5fault zones and down below the river bed, which should eventually require technical study for construction performance and special consideration for possible drought. This text makes mention of the overall construction program and the ongoing construction work at each section.

Japan's First Tunneling Construction by Full-Automatic Jambo ComputerAgatsuma Gorge Tunnel on Prefectural Highway Hayashi Agatsuma Line Tunneling Workpp.15

 By Kazutoshi Hara, Ministry of Land , Infrastructure and Transport

 This is the highway tunnel of 1,768m length proposed for new construction as a part of the ongoing Yamba Dam Construction Project. The reduced volume of overbreak contributes much toward shortening of mucking hours, reduction of lining concrete volume and also of construction costs. For these reasons the project has made use of the Full-Automatic Computer Jambo as the Japan's first attempt. This computer system can allow full-automatic tunnel excavation by input of such basic elements as tunnel alignment, section , blasting pattern and other relevant data available. As compared with manual operation, the automatic excavation system proved its merit by 30 outbreak reduction. This text refers to the working conditions to achieve the economy of scale by this Jambo system, together with its future outlook.

Conquest by TBM over the Worst Ground Using the Well-planned Counter measuresOdori Tunnel Evacuation Adit on Chubu Through Expressway     pp.21

 By Tsutomu Yoshigi, Ministry of Land, Infrastructure & Transport

 This tunnel construction section consists of 2,978m long main tunnel and 3,057m long evacuation tunnel. The Tunnel Boring MachineTBMsystem was adopted to achieve a high speed construction of the evacuation tunnel. After geological survey, five5fault zones were observed in existence throughout the TBM-operated section and possible emerging of fragile soil and rock foundation was expected. Because of this outlook, prior to start of work, strength of the rock foundation was estimated and site geology was being logged out into details by forward prospect boring, together with the well planned auxiliary working methods. After all those efforts, the unstable weak soil ground was conquered by operation of the TBM. This paper mainly mentions what happened during passage through the fault fractured zone and the measures taken by the applicable construction works together with the auxiliary method.

Successful Control over Excavation through Extremely Shallow Overburden under the Existing ExpresswayJo-bando Tunnel on Tsukuba Expresswaypp29

 By Shinichi Suzuki Japan Railway Construction, Transport & Technology Agency

 The tunnel is the a pressure type shield tunnel of 303m length with its segment of 7.3m outside diameter, intersecting with the Joban Expressway at a very small angle. The geology of tunnel section is composed mainly of the water bearing sand layer of slow collapse with N value smaller than 10. The tunnel overburden is at or below one full diameter1Dover the whole section length. For constructional reason, instruments were installed to restrain possible impact upon or to the Joban Expressway, so that quick feedback of the monitored result can be allowed into operational management for excavation.

 This text refers to the excavation results in safety right under the Joban Motorway by setting up the optimum reference values for operation control.

 Tail Race Tunnel Construction with Consideration to Protection of Eagle HawksOkutadami Power Station Extension Projectpp37

 By Atsunori Tonomura, Electric Power Development Co.

 The extension plan envisaged additional construction of power generating units neighbored to the existing Oku-tadami and Ohtori Hydro Power Stations. They are already completed and entered into commercial operation in June 2003. The project area is situated in the national park of natural environment inhabitable for vary rare animals like eagle-hawks. Therefore, effort was made to complete the total project work in only four4years despite the given restriction that the work was allowed only for four4months annually on the earth in consideration of the nest keeping season for eagles. This paper mentions the scheme specifically established for environmental preservation and the concept of how to secure the work schedule and design construction features.

Non destructive Inspection and Deterioration Checkup of Lining Concrete by Surface Wavepp45

 By Takayuki Nakamura, Tokyo Electric Power Co.

 Many of the existing tunnels across the country are in progress with quality deterioration and the need for improved efficient maintenance is increasing.

 Any deformation including cracks as detectable on the lining concrete are detectable mainly by naked eyes, which could by no means reach in depth up to the lining interior. This paper mentions the development process of prospecting both depth and strength of cracks in the lining concrete by use of surface waves and the result of verification on its applicability by testing. On the basis of the inverted analysis results using prospected data, attempt was made to reproduce the progressed working pressure and deformation of the lining.

 In this text, mention is made of the diagnosis model to evaluate both residual bearing force of lining and stability of the tunnel.

Global Strategy by Tunneling Technologies from Japanpp 55

 By Kouichi Ono, Kyoto University Professor & ITA Director

 Japan has been hovering round over this decade, thus allowing close pursuit by Asian countries as well as European nations. It should be brought to attention, however, that tunneling technologies and construction records developed in Japan still keep on the world's highest level, ranking the top in the bridge construction area as well.

 In the realty, however, Japan does not yet come up to the position of World Leader. Indeed, it can not be safely said that Japan is not as yet positively anticipating in the global tunnel and underground construction projects. It seems to be true that advancing effort of Japan's tunneling technologies might be obstructed by complexity of domestic political, economic, educational, R and D scheme and global strategies, etc. With introspection to the present status of Japan, approach is herein made from the viewpoint of worldwide business strategies by means of tunneling strategies toward regeneration of Japan herself.

Special Lecture Forum on ITA Activity and Future Overseas Marketing Strategypp61

 By korehide Miyaguchi, JTA Executive Director

 Upon visit to Japan by the ITA Chairman Mr. A.Assis and Executive Director Mr. C. Berenguire, a request was made to those two gentlemen to hold the special session of lecturing on the theme of the present ITA activities. This is to introduce what was addressed and discussed at that lecture meeting.

 The paper further refers to the strategy on overseas marketing of Japan's tunneling technologies.

 

 

2003

 [Vol. 34, No. 12 December] 2003

Underground Facilities in 'Edo' & Tokyo Eras